Project Description: The project included construction of a 22 MGD sanitary lift station and approximately 320 feet of 30-inch force main to replace the existing lift station on the same site. The new lift station featured a cast-in-place concrete screen channel, wet-well, valve vault, masonry building, submersible pumps with VFD controls, dual channel mechanical screen equipment, equipment hoist, diesel generator, site lighting, and various site improvements. The project also included stream bank and channel stabilization along the perimeter of the site and demolition of the existing lift station to allow space for additional site improvements.

Approximate Construction Cost: $5,500,000

Breadth of Services Provided: Survey, Land Acquisition, Design Engineering, Permitting, Construction Administration