Project Description: United’s Traffic Engineering team tackled this large bundle with intersections at four separate locations. Through coordination with INDOT Central Office ADA reviewers, District Traffic Engineers, and District Construction Engineers, United successfully completed the ADA curb ramp design without the need for a technical inquiry, keeping the project on schedule. Traffic Engineer’s proactively coordinated with a concurrent preventative maintenance contract within the city of Wabash to develop a construction sequence which eliminated rework at the intersection corners caused by the overlap in project scope.
Approximate Project Cost: $3.5 million
Breadth of Services United provided: Survey, RW Verification, Environmental, Signal Design, Railroad Coordination, Utility Coordination