Project Description: The project involves approximately 13,800 feet of new 36-inch and 42-inch relief sewer to provide additional capacity for current wet-weather flows and future development in the Castleton area on the northeast side of Indianapolis. Approximately 2,800 feet of the proposed sewer was installed in areas of high groundwater and difficult soil conditions by the microtunneling method.
Approximate Project Cost: $13,500,000
Breadth of Services Provided: Planning, Survey, Environmental Services, Design Engineering, Permitting, Public Meetings, Land Acquisition, Bidding Services, and Construction Assistance