Project Description: The project included the widening of Gray Road to a four-lane “curb and gutter” section with turning lanes north of 96th Street to Blue Woods Creek. The section continuing north from Blue Woods Creek to 106th Street included a two-lane “curb and gutter” section with a new two-span bridge over Blue Woods Creek. The project also included enclosed storm drainage with grass median and an asphalt multi-use path on the west side of the roadway.
Approximate Project Cost: $4,200,000
Breadth of Services Provided: Survey, Traffic Data Collection & Evaluation, Regulatory Permit Applications, Roadway Design, Bridge Design, Right-of-Way Engineering, Land Acquisition Services, and Construction Inspection